GYPSUM & TUBEWELL, BRIDGE, CANE CRUSHER, D.W.S (HAND PUMPS), DEVELOPMENT OF EXISTING DUG WELL, DIVERSION BUND, Drainage System, Drains & Retaining wall, DUG WELL AND DWS, DWS/CHN LINNING SANITT, ENTEPRISE DEV, FARM TO MARKET ROAD, IMPROVEMENT OF DRAINAGE SYSTEM, Latrines & hand pumps, LINK ROAD, LINING OF MAIN DRAIN, NUCCAS/CHANNEL LINNING, RETAINING WALL & CULVERTS, FARM TO MARKET ROAD, Cane Crusher, Lining of Channel, Tube Well.
District: Charsadda
Donors: Novib , USAID, CIDA
Community PhysicaI Infrastructure Initiated: 193
Community PhysicaI Infrastructure Completed: 191
Beneficiaries:
House Holds: 11,689
Male: 42080
Female: 45587
| District |
CPI Initiated (Nos) |
CPI Completed (Nos) |
Total Cost (Rs.) |
CO Share (Rs.) |
Donor Share (Rs.) |
Avg Project Share (Rs.) |
Amount Disbursed (Rs.) |
| NOVIB |
159 |
158 |
22,828,210 |
3,577,129 |
19,251,081 |
121,842 |
17,922,424 |
| USAID |
32 |
31 |
5,387,050 |
427,350 |
4,959,700 |
159,990 |
4,959,700 |
| CIDA |
2 |
2 |
533,300 |
300 |
533,000 |
266,500 |
533,000 |
| CHARSADDA Region |
193 |
191 |
28,748,560 |
4,004,779 |
24,743,781 |
129,549 |
23,415,124 |
|
|