S# |
Activities |
Target |
Progress |
Outcome |
1 |
Quarterly EFA Forum meetings |
4 |
2 |
- Revitalization of 31inactive EFAs at UC level
- Government systems strengthened in improving service delivery at UC level
- Sustainability of the project ensured through transferring of roles and responsibilities to the main stakeholders
- 20% Enrolment increased through the campaigns of EFA forums.
- Monitoring systems strengthened through the involvement of the UC representator
- Platform provided for advocacy of issues at the grassroot level
|
2 |
Bi-annual publications of Newsletter |
2 |
1 |
- Awareness increased among the masses
- Promotion of best practices of the project highlighted
|
3 |
Signing of MoU/Agreement with the district government |
|
Achieved |
Ownership of the stakeholders ensured by involvement in planning and implementation processes. |
4 |
School Development plans Implementation |
100 |
Under process |
- School based planning strengthened through planning by the PTAs
- System developed at the district level to be replicated by the government itself
- Community participation ensured in planning and implementation
- Effective utilization of government resources.
- Accountability ensured by involvement of stakeholders at the government and community level.
|
5 |
Quarterly meetings with the CCBs formed |
4 |
2 |
- Devolved structure strengthened by involvement of stakeholders at three tiers
- Enhance the developmental activities at the grass root level
- Decentralization of systems strengthened
- Community participation ensured in the planning and implementation
|